We use necessary cookies to make our website work. We'd also like to use optional cookies to understand how you use it, and to help us improve it.

For more information, please read our cookie policy.

Sponsor: Sherburn Aero Club

The aerodrome is located in Class G (uncontrolled) airspace adjacent to Leeds East Airport.

Last updated: 28 May 2025

Framework briefing held with organisations considering proposal of the change (presentation and meeting notes) 26 Oct 16
Sponsor external consultation document (with associated appendices)  
Sponsor's external consultation feedback report  
Sponsor's formal airspace change proposal (date received by CAA) 18 Jan 19
Sponsor's formal airspace change proposal 30 Sep 21
Sponsors airspace change proposal document 08 Nov 21
Following the 'completeness check' the CAA confirms that all ACP documentation has been received from the Sponsor and a redacted version of the Sponsor's final proposal has been published. Any stakeholder may submit a 'call in' requesting that the final decision about changes to the design of UK airspace is made by the Secretary of State for Transport rather than the CAA. The 'call in' window for Sherburn-In-Elmet's Airspace Change Proposal was open from the 21st October to 18th November and no call-in requests were received by the CAA during this time. 26 Nov 19

Following the 'completeness check' the CAA confirms that all ACP documentation has been received from the Sponsor and a redacted version of the Sponsor's final proposal has been published. Any stakeholder may submit a 'call in' requesting that the final decision about changes to the design of UK airspace is made by the Secretary of State for Transport rather than the CAA.

Stakeholders can review the proposal to assess whether or not it meets any of the call in criteria. The 'call in' for this Airspace Change Proposal is open until 28 October 2021. Details on the process and how to submit a request

30 Sep 21

Sponsors update to the CAA meeting minutes

29 Apr 21

Following further discussions with the CAA, the Sponsor has submitted updated documentation to provide clarification on a number of points. This included an updated formal airspace change proposal, clarification questions and an updated Safety Case.

11 Mar 22

Following a request to provide additional information to the CAA as part of the ACPs regulatory assessment, the Sponsor has amended their ACP submission and agreed to publish their safety case. As a result of this, stakeholders have the opportunity to provide feedback on this new information until 8 April 2022.’

Stakeholders can submit feed-back by email to airspace.policy@caa.co.uk

11 Mar 22
This is the latest version of the Sherburn-in-Elmet Pilot Brief, that forms part of the updated document set. 18 Mar 22
Updated Pilot Brief in response to stakeholder feed-back received by the Sponsor 26 Apr 22
Leeds East Airport and Sherburn in Elmet meeting minutes. Westferry House/Online - 31 Mar 22 26 Apr 22
ATM Safety Review - Letter of acceptance  21 March 2023
Updated Safety Case 21 March 2023
Operational assessment by CAA  21 March 2023
Consultation assessment by CAA  
Environmental assessment by CAA 21 March 2023

Decision document (CAA change approval)

Decision Log 

 
Change implementation date

15 June 2023

AIRAC 6 

PIR Data Request Form 10 October 2023

PIR data received from change sponsor

28 May 2025

Following the receipt of the PIR data from the change sponsor, stakeholders have until 1400 on Wednesday 25 June 2025 to submit any feedback on the data that they want the CAA to take into account as we carry out the PIR.

Stakeholders should submit feedback by email to airspace.policy@caa.co.uk and state 'Sherburn-In-Elmet RNAV IAPs PIR (ACP-2015-04)' in the subject heading.

Submissions are limited to one per individual (verified by email address). We give no assurance that we will take account of submissions made outside the feedback window.

28 May 2025
AIRAC distribution date / AIP amendment  
Sponsor's analysis