Sponsor: RAF Brize Norton
Last updated: 11 February 2021
| Framework briefing held with organisations considering proposal of the change | 11 Sept 2014 | 
| Sponsor external consultation document (with associated appendices) | 15 Dec 2017 | 
| Sponsor's external consultation feedback report | 11 October 2018 | 
| Sponsor's formal airspace change proposal (date received by CAA) | 4 August 2020 | 
| Sponsor's additional consultation document | |
| Sponsor's additional consultation feedback report | |
| CAA letter to sponsor | 6 April 2018 | 
| Noise Contour Analysis - CAA response | 25 Sept 2018 | 
| Operational assessment by CAA | 11 Feb 2021 | 
| Consultation assessment by CAA | 11 Feb 2021 | 
| Environmental assessment by CAA | 11 Feb 2021 | 
| Decision document | 11 Feb 2021 | 
    
         
        Provide feedback for this page
    
                