Sponsor: DONG Energy
Implementation of a Transponder Mandatory Zone (TMZ) around the Walney, West of Duddon Sands, Ormonde and Barrow operational wind farms and Walney Extension.
Last updated: 8 March 2019
Decision document (CAA change approval) | 25 Sep 2015 |
Change implementation date | 22 Jul 2017 |
AIRAC distribution date / AIP amendment | AIRC 07/2017 |
PIR initiation date | 10 Jan 2019 |
CAA PIR assessment | 8 Mar 2019 |
Provide feedback for this page