Gatwick Airport Limited (GAL) submitted a proposal to extend the set of commitments, which were due to expire on 31 March 2025, for a further four years.  In May 2025, we decided to accept GAL’s commitments

CAP3113 Final Decision on extending the current commitments, May 2025

This document sets out our final decision to accept GAL’s proposed new commitments for the four-year period from 2025/26 to 2028/29.

Close CAP3113 Final Decision on extending the current commitments, May 2025

CAP3078 Final Proposals on extending the current commitments, February 2025

This document  provides our Final Proposals on these matters and responds to the issues raised by stakeholders following our August 2024 Consultation, including in relation to:

  • GAL’s prices and profitability;
  • uncertainty around capacity expansion;
  • service quality targets; and
  • the scope and timing of a future review of the commitments framework.

We have also published a consultancy report from Grant Thornton (GT) alongside our document.

Responses

Close CAP3078 Final Proposals on extending the current commitments, February 2025