UK Civil Aviation Regulations

These are published by the CAA on our UK Regulations pages. EU Regulations and EASA Access Guides published by EASA no longer apply in the UK. Our website and publications are being reviewed to update all references. Any references to EU law and EASA Access guides should be disregarded and where applicable the equivalent UK versions referred to instead.



Sponsor: DONG Energy

This proposal is to establish a Transponder Mandatory Zone (TMZ) to cover the extension and existing Burbo Bank offshore wind farms. The wind farm will affect the BAE Systems Warton Primary Surveillance Radar and associated operations. The proposed TMZ will cover the development area from the surface to the base on controlled airspace.

Last updated: 5 April 2016

Decision document (CAA change approval)

13 Oct 14
Change implementation date 21 Jul 16
AIRAC distribution date / AIP amendment AIRAC 07 23 Jun 16
PIR initiation date 12 Oct 17
CAA PIR assessment 3 Oct 18