• Sponsor: Liverpool John Lennon Airport

    Implementation of RNAV GNSS Lateral Navigation (LNAV) and combined Lateral/Vertical Navigation (LNAV/VNAV) Instrument Approach Procedures (IAPs) for runways 09 and 27 at Liverpool John Lennon Airport (LJLA).

    Last updated: 28 April 2016

    Framework briefing held with organisations considering proposal of the change 16 Jul 15
    Sponsor's external consultation feedback report 16 Oct 15
    Sponsor's formal airspace change proposal (date received by CAA) 28 Oct 15
    Operational assessment by CAA 10 Feb 16
    Consultation assessment by CAA 14 Dec 15
    Environmental assessment by CAA 01 Mar 16
    Decision document (CAA change approval) 07 Apr 16
    AIRAC distribution date / AIP amendment 12 May 16
    Change implementation date 21 Jul 16
    PIR initiation date TBC
    Sponsor's analysis  
    CAA PIR assessment