• Sponsor: Isle of Scilly Steamship Company (Lands End Airport)

    This proposal is for introduction of GNSS (RNAV) IAPs for each of the runways at Lands End Airport. Introduction of these new procedures is the final stage of an extensive development programme at Lands End Airport to improve the resilience of the vital air-link to the Scilly Isles island-based community and visitors.

    Last updated: 6 March 2017

    Framework briefing held with organisations considering proposal of the change 21 Jul 15
    Sponsor external consultation document (with associated appendices) 18 Aug to 16 Oct 15
    Sponsor's external consultation feedback report 4 Nov 15
    Sponsor's formal airspace change proposal (date received by CAA) 27 Nov 15
    Operational assessment by CAA 2 Feb 16
    Consultation assessment by CAA 22 Dec 15
    Environmental assessment by CAA 4 Feb 16
    Desicion document (CAA change approval) 30 Mar 16
    Change implementation date
    AIRAC distribution date / AIP amendment 22 Apr 16, 1 Jul 16, 20 Jul 16
    PIR initiation date TBD 
    Sponsor's analysis   
    CAA PIR assessment   20 Jul 17